Description
BOILER PLANT RENOVATION PROJECT - REA REOBLIGATE FUNDS DUE TO PRIOR FCP BEING INACCURATE
Base award description: BOILER PLANT RENOVATION PROJECT
Modification chain · 11 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2023-11-21+$14,688,149= $14,688,149
- Mod P000012025-01-08+$0= $14,688,149
- Mod P000022025-02-05+$380,821= $15,068,970
- Mod P000032025-04-03+$69,086= $15,138,056
- Mod P000042025-04-03+$641,048= $15,779,104
- Mod P000052025-08-08+$510,694= $16,289,798
- Mod P000062025-12-08+$0= $16,289,798
- Mod P000072026-05-06+$0= $16,289,798
- Mod P000082026-06-01+$1,222,178= $17,511,975
- Mod P000092026-06-09-$1,222,260= $16,289,715
- Mod P000102026-06-09+$1,222,260= $17,511,975
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2023-11-21 | +$14,688,149 | $14,688,149 | BOILER PLANT RENOVATION PROJECT |
| Mod P00001· OTHER ADMINISTRATIVE ACTION | 2025-01-08 | +$0 | $14,688,149 | BOILER PLANT RENOVATION PROJECT POP EXTENSION |
| Mod P00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2025-02-05 | +$380,821 | $15,068,970 | BOILER PLANT RENOVATION PROJECT IMPLEMENTATION OF LOW NOX REQUIREMENTS |
| Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2025-04-03 | +$69,086 | $15,138,056 | BOILER PLANT RENOVATION PROJECT IMPLEMENTATION OF LOW NOX REQUIREMENTS |
| Mod P00004· CHANGE ORDER | 2025-04-03 | +$641,048 | $15,779,104 | BOILER PLANT RENOVATION PROJECT IMPLEMENTATION OF LOW NOX REQUIREMENTS |
| Mod P00005· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2025-08-08 | +$510,694 | $16,289,798 | BOILER PLANT RENOVATION PROJECT IMPLEMENTATION OF BEI SAFETY DEVICES AND OTHER UNFORESEEN IMPACTS |
| Mod P00006· CHANGE ORDER | 2025-12-08 | +$0 | $16,289,798 | BOILER PLANT RENOVATION PROJECT IMPLEMENTATION OF BEI SAFETY DEVICES AND OTHER UNFORESEEN IMPACTS |
| Mod P00007· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2026-05-06 | +$0 | $16,289,798 | BOILER PLANT RENOVATION PROJECT - POP EXT PER REA |
| Mod P00008· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2026-06-01 | +$1,222,178 | $17,511,975 | BOILER PLANT RENOVATION PROJECT - REA |
| Mod P00009· OTHER ADMINISTRATIVE ACTION | 2026-06-09 | −$1,222,260 | $16,289,715 | BOILER PLANT RENOVATION PROJECT - DEOB TO CHANGE FUND LINES |
| Mod P00010· FUNDING ONLY ACTION | 2026-06-09 | +$1,222,260 | $17,511,975 | BOILER PLANT RENOVATION PROJECT - REA REOBLIGATE FUNDS DUE TO PRIOR FCP BEING INACCURATE |
Related awards · 5
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other recipients under Z1NB from 244-NETWORK CONTRACT OFFICE 4 (36C244) (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| 36C24426N0451 | INNOVATIVE STEAM SOLUTIONS LLC | 244-NETWORK CONTRACT OFFICE 4 (36C244) | $69,878 | FY2026 |
| 36C24422P0304 | POWERHOUSE EQUIPMENT & ENGINEERING CO INC | 244-NETWORK CONTRACT OFFICE 4 (36C244) | $93,380 | FY2022 |
| 36C24422C0008 | PERFORMANCEEPC, LLC | 244-NETWORK CONTRACT OFFICE 4 (36C244) | $121,767 | FY2022 |
| 36C24420F0449 | TRANE U.S. INC. | 244-NETWORK CONTRACT OFFICE 4 (36C244) | $25,000 | FY2020 |
| 36C24418C0240 | TRANE U.S. INC. | 244-NETWORK CONTRACT OFFICE 4 (36C244) | $124,098 | FY2018 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_36C24424C0003_3600_-NONE-_-NONE- · retrieved 2026-09-26.