631-17-002 EXTERIOR SITE IMPROVEMENTS- TIME EXTENSION AT NO COST TO THE GOVERNMENT TO REVIEW AND ACCEPT AS-BUILTS.
Base award description: 631-17-002 EXTERIOR IMPROVEMENTS PROJECT AT VAMC CENTRAL WESTERN MASSACHUSETTS
Modification chain · 10 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2019-09-27+$10,338,568= $10,338,568
- Mod P000012020-09-14+$81,205= $10,419,773
- Mod P000022021-04-05+$0= $10,419,773
- Mod P000032021-05-27+$0= $10,419,773
- Mod P000042021-08-10+$0= $10,419,773
- Mod P000052021-11-04+$0= $10,419,773
- Mod P000062021-12-27+$53,002= $10,472,775
- Mod P000072022-04-28+$11,860= $10,484,635
- Mod P000082022-05-27+$56,759= $10,541,394
- Mod P000092023-03-21+$0= $10,541,394
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2019-09-27 | +$10,338,568 | $10,338,568 | 631-17-002 EXTERIOR IMPROVEMENTS PROJECT AT VAMC CENTRAL WESTERN MASSACHUSETTS |
| Mod P00001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-09-14 | +$81,205 | $10,419,773 | 631-17-002 EXTERIOR IMPROVEMENTS PROJECT AT VAMC CENTRAL WESTERN MASSACHUSETTS-PCO1-4, 6-12-CONSTRUCTION CHANG… |
| Mod P00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-04-05 | +$0 | $10,419,773 | 631-17-002 EXTERIOR SITE-CHANGE SIGNAGE, DELETE CONCRETE WORK, PAVING, CHANGE CURBING, RELOCATE THE FIRE HYDRA… |
| Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-05-27 | +$0 | $10,419,773 | 631-17-002 EXTERIOR SITE-ADDITIONAL ASBESTOS, DELETE FOUNDATION DEMO OF 2 BLGS, DELETE PAVEMENT BEHIND 1 BLDG.… |
| Mod P00004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-08-10 | +$0 | $10,419,773 | 631-17-002 EXTERIOR SITE-MOD TO ADDRESS UNFORESEEN CONDITIONS SUCH AS TEAM TUNNEL, DRAINAGE AND CREDIT FOR PAV… |
| Mod P00005· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-11-04 | +$0 | $10,419,773 | EO14042 - 631-17-002 EXTERIOR SITE IMPROVEMENTS |
| Mod P00006· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-12-27 | +$53,002 | $10,472,775 | 631-17-002 EXTERIOR SITE IMPROVEMENTS-P00006 MOD FOR UNSUITABLE SOILS, MOTORCYCLE PAD, DRAINAGE, DEMOLISH STEA… |
| Mod P00007· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-04-28 | +$11,860 | $10,484,635 | 631-17-002 EXTERIOR SITE IMPROVEMENTS-PCO50 TO FILL ABANDONED STEAM TUNNEL AND NO COST TIME EXTENSION |
| Mod P00008· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-05-27 | +$56,759 | $10,541,394 | 631-17-002 EXTERIOR SITE IMPROVEMENTS-UNFORESEEN ASBESTOS IN THE ABANDONED STEAM TUNNEL, BERM TO ADDRESS UNSAF… |
| Mod P00009· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2023-03-21 | +$0 | $10,541,394 | 631-17-002 EXTERIOR SITE IMPROVEMENTS- TIME EXTENSION AT NO COST TO THE GOVERNMENT TO REVIEW AND ACCEPT AS-BUI… |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI LKC1YLJ12NB4)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| 36C24126N0275 | 241-NETWORK CONTRACT OFFICE 01 (36C241) · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES | $260,078 | FY2026 |
| 36C24125N1137 | 241-NETWORK CONTRACT OFFICE 01 (36C241) · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES | $7,035,438 | FY2025 |
| 36C24125C0067 | 241-NETWORK CONTRACT OFFICE 01 (36C241) · Z1DB · MAINTENANCE OF LABORATORIES AND CLINICS | $1,277,626 | FY2025 |
| 36C24525D0047 | 245-NETWORK CONTRACT OFFICE 5 (36C245) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $0 | FY2025 |
| 36C24125N0383 | 241-NETWORK CONTRACT OFFICE 01 (36C241) · J041 · MAINT/REPAIR/REBUILD OF EQUIPMENT- REFRIGERATION, AIR CONDITIONING, AND AIR CIRCULATING EQUIPMENT | $306,433 | FY2025 |
| 36C24125D0007 | 241-NETWORK CONTRACT OFFICE 01 (36C241) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $0 | FY2025 |
Other recipients under Z1LB from 241-NETWORK CONTRACT OFFICE 01 (36C241) (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| 36C24120N1057 | WILLIAMS BUILDING COMPANY, INC. | 241-NETWORK CONTRACT OFFICE 01 (36C241) | $3,201,217 | FY2020 |
| 36C24119C0058 | BILLY W. JARRETT CONSTRUCTION COMPANY, INC. | 241-NETWORK CONTRACT OFFICE 01 (36C241) | $2,372,924 | FY2019 |
| 36C24118N9816 | MONUMENT CONSTRUCTION LLC | 241-NETWORK CONTRACT OFFICE 01 (36C241) | $590,277 | FY2018 |
| VA24116P1223 | JACKSON RYAN CONSTRUCTION SERVICES, INC. | 241-NETWORK CONTRACT OFFICE 01 (36C241) | $58,000 | FY2016 |
| VA24115J1879 | ALARES CONSTRUCTION INC. | 241-NETWORK CONTRACT OFFICE 01 (36C241) | $2,913 | FY2015 |