Description
REFINISH BUILDING 4 LOWER NORTH:MODIFICATION TO PROVIDE FUNDING FOR CLERICAL ERROR THAT LEFT COSTS OUT IN THE PROPOSAL FROM THE PREVIOUS MODIFICATION TO RAISE THE CONCRETE FLOOR AND DOOR FRAME IN THE ELEVATOR
Base award description: IGF::OT::IGF REFINISH BUILDING 4 LOWER NORTH
Modification chain · 14 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2018-09-21+$2,545,158= $2,545,158
- Mod P000012019-05-08+$170,965= $2,716,123
- Mod P000022019-06-06+$29,907= $2,746,031
- Mod P000032019-06-13+$40,622= $2,786,653
- Mod P000042019-07-18+$249,422= $3,036,075
- Mod P000052019-09-05+$4,939= $3,041,014
- Mod P000062019-12-05+$21,224= $3,062,238
- Mod P000072020-01-17-$313= $3,061,925
- Mod P000082020-01-30+$62,598= $3,124,524
- Mod P000092020-03-03+$10,878= $3,135,402
- Mod P000102020-06-29+$4,064= $3,139,466
- Mod P000112020-09-09+$12,804= $3,152,270
- Mod P000122020-10-21+$15,613= $3,167,883
- Mod P000132020-11-30+$6,120= $3,174,003
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2018-09-21 | +$2,545,158 | $2,545,158 | IGF::OT::IGF REFINISH BUILDING 4 LOWER NORTH |
| Mod P00001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2019-05-08 | +$170,965 | $2,716,123 | IGF::OT::IGF REFINISH BUILDING 4 LOWER NORTH: PCO1 CHANGE TO INCORPORATE ADDITIONAL ACM REMOVAL, REMOVE FALSE… |
| Mod P00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2019-06-06 | +$29,907 | $2,746,031 | IGF::OT::IGF REFINISH BUILDING 4 LOWER NORTH::PCO3 REPAIR UNFORESEEN GLYCOL LEAK INCLUDING REPLACING CORRODED… |
| Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2019-06-13 | +$40,622 | $2,786,653 | IGF::OT::IGF REFINISH BUILDING 4 LOWER NORTH::PCO2 REQUIRES A CHANGE TO ADDRESS UNFORESEEN CONDITIONS FOUND DU… |
| Mod P00004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2019-07-18 | +$249,422 | $3,036,075 | REFINISH BUILDING 4 LOWER NORTH::PCO2 REQUIRES A CHANGE TO ADDRESS UNFORESEEN CONDITIONS FOUND DURING DEMOLITI… |
| Mod P00005· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2019-09-05 | +$4,939 | $3,041,014 | REFINISH BUILDING 4 LOWER NORTH::PCO7 ADDRESS SIGNIFICANT COMPLICATIONS DURING ASBESTOS REMOVAL. ENCAPSULATE A… |
| Mod P00006· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2019-12-05 | +$21,224 | $3,062,238 | REFINISH BUILDING 4 LOWER NORTH:: ADDRESS SPRINKLER PIPE CONFLICTS COP 4 |
| Mod P00007· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-01-17 | −$313 | $3,061,925 | REFINISH BUILDING 4 LOWER NORTH:: MOD P00007 PCO'S 9, 10, AND 12. |
| Mod P00008· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-01-30 | +$62,598 | $3,124,524 | REFINISH BUILDING 4 LOWER NORTH:: MOD P00008 PCO'S 6 AND 8. |
| Mod P00009· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-03-03 | +$10,878 | $3,135,402 | REFINISH BUILDING 4 LOWER NORTH:: MOD P00009-PCO13-ADD AN ELEVATOR KEY, PCO14-ADDITIONAL ELEVATOR ACCESSORIES |
| Mod P00010· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-06-29 | +$4,064 | $3,139,466 | REFINISH BUILDING 4 LOWER NORTH:: MOD P00009-PCO15-CHANGING THE SIZE OF THE GRAB BAR, INSTALLING NEW CAT 6 CAB… |
| Mod P00011· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-09-09 | +$12,804 | $3,152,270 | REFINISH BUILDING 4 LOWER NORTH:: MOD P00010 PCO16-MODIFICATION TO RAISE THE CONCRETE FLOOR IN VESTIBULE, RAIS… |
| Mod P00012· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-10-21 | +$15,613 | $3,167,883 | REFINISH BUILDING 4 LOWER NORTH:MODIFICATION TO PROVIDE FUNDING FOR CLERICAL ERROR THAT LEFT COSTS OUT IN THE… |
| Mod P00013· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-11-30 | +$6,120 | $3,174,003 | REFINISH BUILDING 4 LOWER NORTH:MODIFICATION TO PROVIDE FUNDING FOR CLERICAL ERROR THAT LEFT COSTS OUT IN THE… |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI LKC1YLJ12NB4)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| 36C24126N0275 | 241-NETWORK CONTRACT OFFICE 01 (36C241) · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES | $260,078 | FY2026 |
| 36C24125N1137 | 241-NETWORK CONTRACT OFFICE 01 (36C241) · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES | $7,035,438 | FY2025 |
| 36C24125C0067 | 241-NETWORK CONTRACT OFFICE 01 (36C241) · Z1DB · MAINTENANCE OF LABORATORIES AND CLINICS | $1,277,626 | FY2025 |
| 36C24525D0047 | 245-NETWORK CONTRACT OFFICE 5 (36C245) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $0 | FY2025 |
| 36C24125N0383 | 241-NETWORK CONTRACT OFFICE 01 (36C241) · J041 · MAINT/REPAIR/REBUILD OF EQUIPMENT- REFRIGERATION, AIR CONDITIONING, AND AIR CIRCULATING EQUIPMENT | $306,433 | FY2025 |
| 36C24125D0007 | 241-NETWORK CONTRACT OFFICE 01 (36C241) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $0 | FY2025 |
Other recipients under Z1DA from 241-NETWORK CONTRACT OFFICE 01 (36C241) (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| 36C24126N0735 | ROTHWELL CONSTRUCTION LLC | 241-NETWORK CONTRACT OFFICE 01 (36C241) | $52,452 | FY2026 |
| 36C24126N0673 | ROTHWELL CONSTRUCTION LLC | 241-NETWORK CONTRACT OFFICE 01 (36C241) | $13,144 | FY2026 |
| 36C24126P0504 | AMERICAN DEFENSE INDUSTRIAL, LLC | 241-NETWORK CONTRACT OFFICE 01 (36C241) | $42,389 | FY2026 |
| 36C24126N0664 | MONUMENT CONSTRUCTION SERVICES, LLC | 241-NETWORK CONTRACT OFFICE 01 (36C241) | $42,264 | FY2026 |
| 36C24126N0518 | VETERANS CONSTRUCTION LLC | 241-NETWORK CONTRACT OFFICE 01 (36C241) | $169,664 | FY2026 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_36C24118N1569_3600_VA24113D0039MATOC_3600 · retrieved 2026-09-26.