Description
MIRAMAR NATIONAL CEMETERY EXPANSION PHASE 2 MODIFICATION TO ADDRESS EXTENDED GENERAL CONDITIONS.
Base award description: MIRAMAR NATIONAL CEMETERY EXPANSION PHASE 2
Modification chain · 20 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2021-09-23+$29,948,101= $29,948,101
- Mod P000012022-03-18+$385,336= $30,333,437
- Mod P000022022-04-28+$488,000= $30,821,437
- Mod P000032022-08-18+$25,569= $30,847,006
- Mod A000012022-08-25+$57,056= $30,904,062
- Mod A000022023-01-31+$225,662= $31,129,723
- Mod A000032023-01-31+$120,209= $31,249,933
- Mod A000042023-03-23+$209,891= $31,459,823
- Mod A000052023-05-22+$58,049= $31,517,872
- Mod A000062023-05-22+$83,053= $31,600,926
- Mod P000072023-05-22+$546,887= $32,147,813
- Mod P000082023-06-08+$0= $32,147,813
- Mod A000092023-09-08+$193,662= $32,341,475
- Mod P000102023-11-24+$62,692= $32,404,167
- Mod P000112024-02-14+$250,341= $32,654,508
- Mod A000122024-04-29+$247,227= $32,901,734
- Mod A000132024-07-01+$71,044= $32,972,778
- Mod A000142024-07-30+$228,682= $33,201,460
- Mod A000152025-01-30+$101,729= $33,303,188
- Mod A000162025-09-25+$38,999= $33,342,187
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2021-09-23 | +$29,948,101 | $29,948,101 | MIRAMAR NATIONAL CEMETERY EXPANSION PHASE 2 |
| Mod P00001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-03-18 | +$385,336 | $30,333,437 | MIRAMAR NATIONAL CEMETERY EXPANSION PHASE 2 DISPOSAL OF UNDOCUMENTED SPOILS. |
| Mod P00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-04-28 | +$488,000 | $30,821,437 | MIRAMAR NATIONAL CEMETERY EXPANSION PHASE 2 SUPPLEMENT AGREEMENT FOR HARD ROCK EXCAVATION AT SITE. |
| Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-08-18 | +$25,569 | $30,847,006 | MIRAMAR NATIONAL CEMETERY EXPANSION PHASE 2 SUPPLEMENT AGREEMENT FOR HARD ROCK EXCAVATION AT SITE. THIS SA IS… |
| Mod A00001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-08-25 | +$57,056 | $30,904,062 | MIRAMAR NATIONAL CEMETERY EXPANSION PHASE 2 |
| Mod A00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2023-01-31 | +$225,662 | $31,129,723 | MIRAMAR NATIONAL CEMETERY EXPANSION PHASE 2 ADMINISTRATIVE BUILDING MODIFICATIONS. |
| Mod A00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2023-01-31 | +$120,209 | $31,249,933 | MIRAMAR NATIONAL CEMETERY EXPANSION PHASE 2 |
| Mod A00004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2023-03-23 | +$209,891 | $31,459,823 | MIRAMAR NATIONAL CEMETERY EXPANSION PHASE 2 |
| Mod A00005· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2023-05-22 | +$58,049 | $31,517,872 | MIRAMAR NATIONAL CEMETERY EXPANSION PHASE 2 MISCELLANEOUS SITE ELECTRICAL |
| Mod A00006· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2023-05-22 | +$83,053 | $31,600,926 | MIRAMAR NATIONAL CEMETERY EXPANSION PHASE 2 MAINTENANCE FACILITY & HONOR GUARD |
| Mod P00007· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2023-05-22 | +$546,887 | $32,147,813 | MIRAMAR NATIONAL CEMETERY EXPANSION PHASE 2 MODIFICATION FOR NOBEL DR. TURN LANE REDESIGN. |
| Mod P00008· OTHER ADMINISTRATIVE ACTION | 2023-06-08 | +$0 | $32,147,813 | MIRAMAR NATIONAL CEMETERY EXPANSION PHASE 2 MODIFICATION TO CHANGE PO NUMBER |
| Mod A00009· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2023-09-08 | +$193,662 | $32,341,475 | MIRAMAR NATIONAL CEMETERY EXPANSION PHASE 2 MODIFICATION TO ADD ADDITIONAL SITE WORK. |
| Mod P00010· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2023-11-24 | +$62,692 | $32,404,167 | MIRAMAR NATIONAL CEMETERY EXPANSION PHASE 2 MODIFICATION TO REPAIR LEAK IN MAINTENANCE ROAD. |
| Mod P00011· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2024-02-14 | +$250,341 | $32,654,508 | MIRAMAR NATIONAL CEMETERY EXPANSION PHASE 2 MODIFICATION TO ADDRESS MULTIPLE COR'S. |
| Mod A00012· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2024-04-29 | +$247,227 | $32,901,734 | MIRAMAR NATIONAL CEMETERY EXPANSION PHASE 2 MODIFICATION TO ADDRESS MULTIPLE COR'S. |
| Mod A00013· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2024-07-01 | +$71,044 | $32,972,778 | MIRAMAR NATIONAL CEMETERY EXPANSION PHASE 2 MODIFICATION TO ADDRESS MULTIPLE COR'S. |
| Mod A00014· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2024-07-30 | +$228,682 | $33,201,460 | MIRAMAR NATIONAL CEMETERY EXPANSION PHASE 2 MODIFICATION TO ADDRESS EXTENDED GENERAL CONDITIONS. |
| Mod A00015· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2025-01-30 | +$101,729 | $33,303,188 | MIRAMAR NATIONAL CEMETERY EXPANSION PHASE 2 MODIFICATION TO ADDRESS EXTENDED GENERAL CONDITIONS. |
| Mod A00016· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2025-09-25 | +$38,999 | $33,342,187 | MIRAMAR NATIONAL CEMETERY EXPANSION PHASE 2 MODIFICATION TO ADDRESS EXTENDED GENERAL CONDITIONS. |
Related awards · 7
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI ENM4H2KY1PV9)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| 36C10F23C0008 | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) · Y1PC · CONSTRUCTION OF UNIMPROVED REAL PROPERTY (LAND) | $42,010,850 | FY2023 |
| 36C78623C0017 | NATIONAL CEMETERY ADMIN (36C786) · Y1PZ · CONSTRUCTION OF OTHER NON-BUILDING FACILITIES | $11,857,366 | FY2023 |
Other recipients under Y1PC from OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| 36C10F26C0005 | GC & V CONSTRUCTION LLC | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $59,890,000 | FY2026 |
| 36C10F25C0007 | HAMILTON PACIFIC CHAMBERLAIN LLC | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $637,437 | FY2025 |
| 36C10F24C0007 | SEABEE CONSTRUCTION, INC. | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $79,106,191 | FY2024 |
| 36C10F24C0001 | RBVETCO, LLC | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $38,940,668 | FY2024 |
| 36C10F22C0016 | RANDY KINDER EXCAVATING INC | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $20,321,493 | FY2022 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_36C10F21C0017_3600_-NONE-_-NONE- · retrieved 2026-09-25.