Description
DELAY COSTS ASSOCIATED WITH MODIFICATION NOS. P00032 AND P00034, SWEEPER JET PUMP RE-PIPING
Base award description: CONSTRUCTION CENTRAL UTILITY PLANT
Modification chain · 44 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2021-06-28+$9,205,000= $9,205,000
- Mod P000012022-03-07+$74,811= $9,279,811
- Mod P000022022-03-31+$15,768= $9,295,579
- Mod P000032022-05-04+$20,010= $9,315,589
- Mod P000042022-05-25+$35,165= $9,350,754
- Mod P000062022-07-26+$40,626= $9,391,379
- Mod P000052022-08-08+$210,878= $9,602,257
- Mod P000072022-08-09+$41,268= $9,643,525
- Mod P000082022-09-30+$380,568= $10,024,093
- Mod P000092022-11-04+$159,634= $10,183,727
- Mod P000102022-12-17+$14,595= $10,198,323
- Mod P000112023-03-06+$66,752= $10,265,075
- Mod P000122023-04-21+$0= $10,265,075
- Mod P000132023-05-23+$0= $10,265,075
- Mod P000142023-05-24+$7,268= $10,272,342
- Mod P000152023-06-28+$23,983= $10,296,325
- Mod P000162023-08-17+$0= $10,296,325
- Mod P000172023-08-29+$516,583= $10,812,908
- Mod P000182023-09-18+$10,910= $10,823,818
- Mod P000202023-12-22+$9,647= $10,833,464
- Mod P000212024-01-04+$1,100= $10,834,564
- Mod P000222024-01-23+$394= $10,834,958
- Mod P000232024-01-26+$1,567= $10,836,525
- Mod P000242024-01-26+$5,089= $10,841,614
- Mod P000252024-01-26+$6,630= $10,848,244
- Mod P000262024-02-09+$3,881= $10,852,124
- Mod P000272024-02-09+$7,327= $10,859,451
- Mod P000282024-02-16+$19,356= $10,878,807
- Mod P000292024-02-22+$5,669= $10,884,476
- Mod P000302024-03-04+$37,353= $10,921,829
- Mod P000312024-03-26+$24,876= $10,946,704
- Mod P000322024-03-28+$29,278= $10,975,983
- Mod P000332024-03-28+$43,958= $11,019,941
- Mod P000192024-03-29+$0= $11,019,941
- Mod P000342024-04-25+$0= $11,019,941
- Mod P000352024-05-02+$49,811= $11,069,751
- Mod P000362024-06-05+$1,365= $11,071,117
- Mod P000372024-07-02-$7,897= $11,063,220
- Mod P000382024-07-02-$21,826= $11,041,394
- Mod P000392024-07-26+$29,794= $11,071,188
- Mod P000402024-08-07+$305,376= $11,376,564
- Mod P000412024-08-28+$8,910= $11,385,474
- Mod P000422024-09-11-$12,073= $11,373,401
- Mod P000432024-12-02+$774,561= $12,147,962
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2021-06-28 | +$9,205,000 | $9,205,000 | CONSTRUCTION CENTRAL UTILITY PLANT |
| Mod P00001· CHANGE ORDER | 2022-03-07 | +$74,811 | $9,279,811 | P00001 CO-01 PIER RELOCATION- CONSTRUCTION CENTRAL UTILITY PLANT |
| Mod P00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-03-31 | +$15,768 | $9,295,579 | TOWER 6 LEAK (UNSEEN CONDITION)CONSTRUCTION CENTRAL UTILITY PLANT |
| Mod P00003· DEFINITIZE CHANGE ORDER | 2022-05-04 | +$20,010 | $9,315,589 | P00003 TO DEFINITIZE P00001 PIER RELOCATION CONSTRUCTION CENTRAL UTILITY PLANT |
| Mod P00004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-05-25 | +$35,165 | $9,350,754 | P00004 VFD INTERFERENCE FOR CUP CONSTRUCTION |
| Mod P00006· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-07-26 | +$40,626 | $9,391,379 | P00006 2ND TOWER 6 FLOOD CUP CONSTRUCTION |
| Mod P00005· CHANGE ORDER | 2022-08-08 | +$210,878 | $9,602,257 | P00005 UNILATERAL ASI002 REVISIONS CUP CONSTRUCTION VA DALLAS |
| Mod P00007· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-08-09 | +$41,268 | $9,643,525 | P00007 CAISSON DRILLING- UNSEEN SITE CONDITIONS |
| Mod P00008· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-09-30 | +$380,568 | $10,024,093 | P00008 DEFINITIZE P00005 ASI002 REV CUP CONSTRUCTION |
| Mod P00009· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-11-04 | +$159,634 | $10,183,727 | P00009 COMPENSABLE TIME EXTENSION |
| Mod P00010· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-12-17 | +$14,595 | $10,198,323 | 1ST TOWER 6 FLOOD |
| Mod P00011· CHANGE ORDER | 2023-03-06 | +$66,752 | $10,265,075 | CHANGE ORDER ASI 003-CUP CONSTRUCTION |
| Mod P00012· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2023-04-21 | +$0 | $10,265,075 | CONTRACT EXTENSION DUE TO COVID DELAYS |
| Mod P00013· OTHER ADMINISTRATIVE ACTION | 2023-05-23 | +$0 | $10,265,075 | IFAMS OBLIGATION TRANSITION |
| Mod P00014· CHANGE ORDER | 2023-05-24 | +$7,268 | $10,272,342 | CO-04 EPOXY REPAIR BASINS 6 |
| Mod P00015· CHANGE ORDER | 2023-06-28 | +$23,983 | $10,296,325 | CO-05 EMERGENCY A/C REPAIR RE TRAILER |
| Mod P00016· CHANGE ORDER | 2023-08-17 | +$0 | $10,296,325 | CO-06 TIME EXTENSION PENDING FINAL NEGOTIATIONS FOR ASI-003 |
| Mod P00017· DEFINITIZE CHANGE ORDER | 2023-08-29 | +$516,583 | $10,812,908 | DEFINITIZE ASI003 P00011 AND P00016 |
| Mod P00018· DEFINITIZE CHANGE ORDER | 2023-09-18 | +$10,910 | $10,823,818 | DEFINITIZE CO-05 P00015 |
| Mod P00020· CHANGE ORDER | 2023-12-22 | +$9,647 | $10,833,464 | CHANGE ORDER DIRECTIVE TO RELOCATE GREENLAND TRAILER-CUP CONSTRUCTION |
| Mod P00021· CHANGE ORDER | 2024-01-04 | +$1,100 | $10,834,564 | CHANGE ORDER DIRECTIVE TO EMERGENCY RELUBE CCU-5-CUP CONSTRUCTION |
| Mod P00022· DEFINITIZE CHANGE ORDER | 2024-01-23 | +$394 | $10,834,958 | DEFINITIZE CHANGE ORDER DIRECTIVE TO EMERGENCY RELUBE CCU-5-CUP CONSTRUCTION |
| Mod P00023· DEFINITIZE CHANGE ORDER | 2024-01-26 | +$1,567 | $10,836,525 | DEFINITIZE P00014 |
| Mod P00024· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2024-01-26 | +$5,089 | $10,841,614 | EXTEND CONCRETE APRON OF CT 6,7 & 8. |
| Mod P00025· CHANGE ORDER | 2024-01-26 | +$6,630 | $10,848,244 | CHANGE ORDER DIRECTIVE UNSEEN CONDITIONS IN RESPONSE TO RFI 86 & 101 BASIN #4 SUMP PIT. |
| Mod P00026· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2024-02-09 | +$3,881 | $10,852,124 | PREVENTATIVE MAINTENANCE OF NEW CHILLER 70-CCU5 (1ST RELUBRICATION) |
| Mod P00027· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2024-02-09 | +$7,327 | $10,859,451 | RESPONSE TO RFI 53 ELECTRICAL CONCRETE PAD AS RELATED TO ASI002 COMPLETED. |
| Mod P00028· CHANGE ORDER | 2024-02-16 | +$19,356 | $10,878,807 | RESPONSE TO RFI 109 AND REVISED SOW FOR ADDITIONAL & DEDUCTED CONCRETE WORK, RELOCATION OF CHAIN LINK FENCE EX… |
| Mod P00029· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2024-02-22 | +$5,669 | $10,884,476 | RESPONSE TO RFI 105 SUMP PIT GRATE REPLACEMENT. |
| Mod P00030· CHANGE ORDER | 2024-03-04 | +$37,353 | $10,921,829 | CO-11 DIRECTION TO BEGIN WORK TO INSTALL SLUICE GATE BETWEEN COOLING TOWERS 5 & 6 |
| Mod P00031· DEFINITIZE CHANGE ORDER | 2024-03-26 | +$24,876 | $10,946,704 | DEFINITIZE CHANGE ORDER - RFI 70 GLIDEN ROAD POUR BACK |
| Mod P00032· CHANGE ORDER | 2024-03-28 | +$29,278 | $10,975,983 | CO-12 - SWEEPER JET PIPING REDO |
| Mod P00033· CHANGE ORDER | 2024-03-28 | +$43,958 | $11,019,941 | CO-12 - SWEEPER JET PIPING REDO |
| Mod P00019· OTHER ADMINISTRATIVE ACTION | 2024-03-29 | +$0 | $11,019,941 | ADM MODIFICATION TO CORRECT DOLLAR VALUE TYPO IN BLOCK 12 |
| Mod P00034· OTHER ADMINISTRATIVE ACTION | 2024-04-25 | +$0 | $11,019,941 | ADM MODIFICATION TO CORRECT SOW FOR CO-12 AND CO-13 PROVIDED IN MODIFICATIONS P00032 AND P00033. |
| Mod P00035· CHANGE ORDER | 2024-05-02 | +$49,811 | $11,069,751 | CO-14 VFD FANS AND GRAVEL INSTALLATION |
| Mod P00036· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2024-06-05 | +$1,365 | $11,071,117 | FURNISH ELECTRICAL PULL BOXES (4) |
| Mod P00037· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2024-07-02 | −$7,897 | $11,063,220 | INSTALL SLUICE GATE BECAUSE THE OPERATION OF THE TOWERS REQUIRES AN EQUAL LEVEL OF WATER TO PREVENT OVERFLOWIN… |
| Mod P00038· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2024-07-02 | −$21,826 | $11,041,394 | CONTRACTOR TO PERFORM ALL WORK ASSOCIATED WITH CONCRETE APRONS. |
| Mod P00039· DEFINITIZE CHANGE ORDER | 2024-07-26 | +$29,794 | $11,071,188 | CONTRACTOR TO PERFORM ALL WORK ASSOCIATED WITH JOBSITE TRAILER RELOCATION. |
| Mod P00040· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2024-08-07 | +$305,376 | $11,376,564 | P00040 SA SETTLEMENT FOR DELAY IN TURNOVER OF EXISTING COOLING TOWERS 5&6. |
| Mod P00041· DEFINITIZE CHANGE ORDER | 2024-08-28 | +$8,910 | $11,385,474 | PERFORM ALL WORK ASSOCIATED WITH MODIFYING THE CONCRETE, FENCING, LANDSCAPING AND SPRINKLER SYSTEM PER THE REV… |
| Mod P00042· DEFINITIZE CHANGE ORDER | 2024-09-11 | −$12,073 | $11,373,401 | INSTALL GRAVEL ON WEST SIDE OF COOLING TOWER AREA. |
| Mod P00043· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2024-12-02 | +$774,561 | $12,147,962 | DELAY COSTS ASSOCIATED WITH MODIFICATION NOS. P00032 AND P00034, SWEEPER JET PUMP RE-PIPING |
Related awards · 7
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI GTP8S87MBPF3)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| 36C24621P1806 | 246-NETWORK CONTRACTING OFFICE 6 (36C246) · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES | $11,080 | FY2021 |
| 36C26018N1284 | 260-NETWORK CONTRACT OFFICE 20 (36C260) · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES | $2,000 | FY2018 |
| 36C24618C0099 | 246-NETWORK CONTRACTING OFFICE 6 (36C246) · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES | $7,725,310 | FY2018 |
| 36C24118N9689 | 241-NETWORK CONTRACT OFFICE 01 (36C241) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $4,189,107 | FY2018 |
| 36C24118N9722 | 241-NETWORK CONTRACT OFFICE 01 (36C241) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $1,125,020 | FY2018 |
| 36C26018N1050 | 260-NETWORK CONTRACT OFFICE 20 (36C260) · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES | $5,032,925 | FY2018 |
Other recipients under Y1NB from OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| 36C10F25C50005 | SGJV2, LLC | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $77,604,919 | FY2025 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_36C10F21C0009_3600_-NONE-_-NONE- · retrieved 2026-09-25.