Description
OHIO WESTERN RESERVE PHASE III CONSTRUCTION A00100 (NO COST MOD FOR STORMWATER AND SITE WORK, RFIS 136 AND 137)
Base award description: CONSTRUCTION OF OHIO WESTERN RESERVE NATIONAL CEMETERY, PHASE 3
Modification chain · 109 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2020-09-15+$24,284,369= $24,284,369
- Mod P001062020-09-16+$347,125= $24,631,494
- Mod A000012021-01-11+$41,423= $24,672,917
- Mod A000022021-01-13+$13,527= $24,686,444
- Mod A000032021-01-21+$16,675= $24,703,119
- Mod A000042021-01-28+$12,964= $24,716,083
- Mod A000052021-02-01+$15,600= $24,731,683
- Mod A000062021-02-04-$38,679= $24,693,004
- Mod A000072021-03-26+$1,551= $24,694,555
- Mod A000082021-03-30+$4,435= $24,698,990
- Mod A000092021-04-01+$758= $24,699,748
- Mod A000102021-04-08+$10,486= $24,710,234
- Mod A000112021-04-27+$4,420= $24,714,654
- Mod A000122021-05-06+$2,434= $24,717,088
- Mod A000132021-05-06+$3,323= $24,720,411
- Mod A000142021-06-01+$32,111= $24,752,522
- Mod A000152021-06-01+$2,972= $24,755,494
- Mod A000162021-06-08+$1,214= $24,756,708
- Mod A000172021-06-15+$0= $24,756,708
- Mod A000182021-06-28+$6,914= $24,763,622
- Mod A000192021-07-20+$41,859= $24,805,481
- Mod A000202021-08-03+$0= $24,805,481
- Mod A000212021-08-04+$1,602= $24,807,083
- Mod A000222021-09-09+$25,970= $24,833,053
- Mod A000232021-09-30+$161,082= $24,994,135
- Mod A000242021-10-14+$251,429= $25,245,564
- Mod A000252021-10-19+$5,023= $25,250,587
- Mod A000262021-10-22+$28,627= $25,279,214
- Mod A000272021-11-04+$4,390= $25,283,604
- Mod A000282021-11-04+$5,954= $25,289,558
- Mod A000292021-11-17+$21,454= $25,311,012
- Mod A000302021-12-17+$33,422= $25,344,434
- Mod A000312021-12-22+$11,772= $25,356,206
- Mod A000322021-12-22+$7,643= $25,363,849
- Mod A000332021-12-22+$13,736= $25,377,585
- Mod A000342021-12-27+$15,025= $25,392,610
- Mod A000352022-01-10+$24,383= $25,416,993
- Mod A000362022-01-10+$17,929= $25,434,922
- Mod A000372022-01-14+$842= $25,435,764
- Mod A000382022-01-14+$838= $25,436,602
- Mod A000392022-01-27+$657= $25,437,259
- Mod A000402022-01-28+$19,007= $25,456,266
- Mod A000412022-02-07+$739= $25,457,005
- Mod A000422022-02-07+$76,659= $25,533,664
- Mod P000432022-03-02+$317,404= $25,851,068
- Mod A000442022-03-08+$13,953= $25,865,021
- Mod A000452022-03-14+$4,022= $25,869,043
- Mod A000462022-03-15+$7,395= $25,876,438
- Mod A000472022-03-21+$8,928= $25,885,366
- Mod A000482022-03-22+$11,871= $25,897,237
- Mod A000492022-03-29+$5,686= $25,902,923
- Mod A000502022-04-21+$50,000= $25,952,923
- Mod A000512022-04-27+$0= $25,952,923
- Mod A000522022-04-29+$0= $25,952,923
- Mod A000532022-05-02+$65,904= $26,018,827
- Mod A000542022-05-09+$1,064= $26,019,891
- Mod A000552022-05-11+$79,511= $26,099,402
- Mod A000562022-06-03+$48,876= $26,148,278
- Mod A000572022-06-09+$3,628= $26,151,906
- Mod A000582022-06-13+$168,498= $26,320,404
- Mod A000592022-06-15+$62,635= $26,383,039
- Mod A000602022-06-27+$8,572= $26,391,611
- Mod A000612022-06-30+$126,263= $26,517,874
- Mod A000622022-07-15+$17,251= $26,535,125
- Mod A000632022-07-22+$4,068= $26,539,193
- Mod A000642022-07-26+$53,412= $26,592,605
- Mod A000652022-08-02+$16,461= $26,609,066
- Mod A000662022-08-02+$8,716= $26,617,782
- Mod A000672022-08-08+$42,549= $26,660,331
- Mod A000682022-08-24+$8,077= $26,668,408
- Mod A000692022-08-25+$12,375= $26,680,783
- Mod A000702022-09-12+$8,663= $26,689,446
- Mod A000712022-10-25+$1,720= $26,691,166
- Mod P000722022-12-30+$600,000= $27,291,166
- Mod A000732023-01-04+$70,366= $27,361,532
- Mod A000742023-01-04+$19,751= $27,381,283
- Mod A000752023-01-09+$18,781= $27,400,064
- Mod A000762023-01-19+$10,000= $27,410,064
- Mod A000772023-01-31+$38,659= $27,448,723
- Mod A000782023-02-06+$6,733= $27,455,456
- Mod A000792023-02-10+$19,069= $27,474,525
- Mod A000802023-02-21+$4,636= $27,479,161
- Mod A000812023-02-24+$5,546= $27,484,707
- Mod A000822023-03-06+$7,279= $27,491,986
- Mod A000832023-03-14+$11,999= $27,503,985
- Mod A000842023-03-15+$4,235= $27,508,220
- Mod A000852023-03-23+$55,551= $27,563,771
- Mod P000862023-04-03+$237,057= $27,800,828
- Mod A000872023-04-05+$25,761= $27,826,589
- Mod A000882023-05-09+$10,809= $27,837,398
- Mod A000892023-05-09+$2,956= $27,840,354
- Mod P000902023-06-09+$0= $27,840,354
- Mod P000932023-07-20+$150,000= $27,990,354
- Mod A000912023-07-27+$66,097= $28,056,451
- Mod A000922023-07-27+$6,761= $28,063,212
- Mod A000942023-08-01+$55,167= $28,118,379
- Mod A000952023-08-15+$76,824= $28,195,203
- Mod A000962023-09-22+$54,540= $28,249,743
- Mod A000972023-09-29+$19,937= $28,269,680
- Mod A000982023-11-03+$49,769= $28,319,449
- Mod A000992023-12-13+$33,868= $28,353,317
- Mod A001012024-01-24+$196,556= $28,549,873
- Mod A001022024-02-12+$187,497= $28,737,370
- Mod A001032024-02-14+$95,546= $28,832,916
- Mod A001042024-05-07+$244,271= $29,077,187
- Mod A001052024-05-07+$185,785= $29,262,972
- Mod A001072024-11-13+$120,114= $29,383,086
- Mod A001082024-12-17+$43,502= $29,426,588
- Mod A001002024-12-23+$0= $29,426,588
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2020-09-15 | +$24,284,369 | $24,284,369 | CONSTRUCTION OF OHIO WESTERN RESERVE NATIONAL CEMETERY, PHASE 3 |
| Mod P00106· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-09-16 | +$347,125 | $24,631,494 | ADDITIONAL IRRIGATION REPAIRS AND STARTUP |
| Mod A00001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-01-11 | +$41,423 | $24,672,917 | OWRNC, PHASE 3, SEVILLE, OH |
| Mod A00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-01-13 | +$13,527 | $24,686,444 | SA-A00002 - REMEDIATE SOILS FOR TEMPORARY CONSTRUCTION ROAD/LAYDOWN AREA |
| Mod A00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-01-21 | +$16,675 | $24,703,119 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION SA-A00003, RELOCATE RESIDENT ENGINEER FIELD OFFICE AND PARKING |
| Mod A00004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-01-28 | +$12,964 | $24,716,083 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION SA-A00004, INSTALL WATER ISOLATION VALVES FOR THE PUBLIC INFORMATION C… |
| Mod A00005· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-02-01 | +$15,600 | $24,731,683 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION SA-A00005, CLEAR ADDITIONAL AREA FOR EXPANSION LANDSCAPING |
| Mod A00006· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-02-04 | −$38,679 | $24,693,004 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION SA-A00006, IMPLEMENT CONCRETE FINISH CHANGES (RFI-001) |
| Mod A00007· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-03-26 | +$1,551 | $24,694,555 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION SA-A00007, UPGRADE IRRIGATION OPERATING SYSTEM FROM IQ3 TO IQ4 |
| Mod A00008· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-03-30 | +$4,435 | $24,698,990 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION SA-A00008, PROVIDE SCANNER TO RE FIELD OFFICE FOR RED-LINE DRAWINGS |
| Mod A00009· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-04-01 | +$758 | $24,699,748 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION SA-A00009, INSTALL SANITARY NAPKIN DISPOSAL RECEPTACLES AT PIC |
| Mod A00010· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-04-08 | +$10,486 | $24,710,234 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION SA-A00010, REPLACE STATIONARY BOLLARDS AT ADMIN BUILDING WITH REMOVABL… |
| Mod A00011· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-04-27 | +$4,420 | $24,714,654 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION SA-A00011, PROVIDE ADDITIONAL CONCRETE FOR COLUMBARIUM (RFI 025) |
| Mod A00012· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-05-06 | +$2,434 | $24,717,088 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION SA-A00012, ACCELERATE INSTALLATION OF UNINTERRUPTABLE POWER SUPPLY (UP… |
| Mod A00013· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-05-06 | +$3,323 | $24,720,411 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION SA-A00013, ADDITIONAL CLEARING AND GRUBBING - EXPANSION AREA |
| Mod A00014· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-06-01 | +$32,111 | $24,752,522 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION SA-A00014, CORRECT PRICING OF CONCRETE FINISH ACRYLIC PAINT FOR SA-A00… |
| Mod A00015· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-06-01 | +$2,972 | $24,755,494 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION SA-A00015, UPGRADE REDLINE SCANNER |
| Mod A00016· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-06-08 | +$1,214 | $24,756,708 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION SA-A00016, UNDERPIN EXISTING MATERIAL STORAGE AREA |
| Mod A00017· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-06-15 | +$0 | $24,756,708 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION AD-A00017, WEATHER IMPACT TO SCHEDULE (NOV 2020 TO APR 2021) |
| Mod A00018· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-06-28 | +$6,914 | $24,763,622 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION SA-A00018, PROVIDE STENCILING FOR NUMBERING OF PPC CRYPTS |
| Mod A00019· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-07-20 | +$41,859 | $24,805,481 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION SA-A00019, REMOVE AND REPLACE METAL SIDING OF EXISTING MATERIAL STORAG… |
| Mod A00020· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-08-03 | +$0 | $24,805,481 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION AD-A00020, AUTHORIZE MATERIAL OFFSITE STORAGE (LAKELAND ELECTRIC) |
| Mod A00021· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-08-04 | +$1,602 | $24,807,083 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION SA-A00021, PROVIDE ADDITIONAL PRINTERS FOR THE RE OFFICE |
| Mod A00022· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-09-09 | +$25,970 | $24,833,053 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION SA-A00022, PROVIDE ADDITIONAL PLYWOOD FORMS FOR COLUMBARIUM WALLS |
| Mod A00023· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-09-30 | +$161,082 | $24,994,135 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION SA-A00023, REPLACE UNSUITABLE SOILS, SECTION 25 |
| Mod A00024· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-10-14 | +$251,429 | $25,245,564 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION SA-A00024, REMOVE EXCESS TOPSOIL FROM EXPANSION AREA |
| Mod A00025· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-10-19 | +$5,023 | $25,250,587 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION SA-A00025, REROUTE SECTION 23 UNDERDRAINS TO CBMH-14 |
| Mod A00026· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-10-22 | +$28,627 | $25,279,214 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION SA-A00026, UNDERCUT SOILS WITH EXCESSIVE MOISTURE PPC SECTIONS 22 AND… |
| Mod A00027· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-11-04 | +$4,390 | $25,283,604 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION SA-A00027, INSTALLATION OF ADDITIONAL TRAFFIC BOLLARDS FOR WELL #2 |
| Mod A00028· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-11-04 | +$5,954 | $25,289,558 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION SA-A00028, MODIFY FLASHING DETAIL ON COLUMBARIUM END COLUMNS |
| Mod A00029· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-11-17 | +$21,454 | $25,311,012 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION SA-A00029, INSTALL WEATHER CURTAIN STRIPS FOR MATERIAL STORAGE BINS |
| Mod A00030· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-12-17 | +$33,422 | $25,344,434 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION SA-A00030, ACCELERATE MASONRY WORK DUE TO CONTRACT PROTEST |
| Mod A00031· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-12-22 | +$11,772 | $25,356,206 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION SA-A00031, INSTALL TEMPORARY CONSTRUCTION SIGNAGE/DISPLAY CASE |
| Mod A00032· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-12-22 | +$7,643 | $25,363,849 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION SA-A00032, PROVIDE ADDITIONAL SURVEY (MAINTENANCE YARD AND MEMORIAL WA… |
| Mod A00033· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-12-22 | +$13,736 | $25,377,585 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION SA-A00033, REPLACE INSULATION AT PUMP HOUSE |
| Mod A00034· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-12-27 | +$15,025 | $25,392,610 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION SA-A00034, RECONFIGURE PRE-PLACED OVERSIZED CRYPT SECTION 25 |
| Mod A00035· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-01-10 | +$24,383 | $25,416,993 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION SA-A00035, MODIFY SIGNAGE REQUIREMENTS |
| Mod A00036· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-01-10 | +$17,929 | $25,434,922 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION SA-A00036, RECONFIGURE IRRIGATION SYSTEM FOR EXISTING BURIAL SECTIONS… |
| Mod A00037· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-01-14 | +$842 | $25,435,764 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION SA-A00037, COMPLETE FRAGNETS FOR GOVERNMENT RFPS NOT AWARDED |
| Mod A00038· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-01-14 | +$838 | $25,436,602 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION SA-A00038, ADDED REINFORCING DOWELS AT SALT BUILDING PAVEMENT |
| Mod A00039· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-01-27 | +$657 | $25,437,259 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION SA-A00039, ADDED BLOCKING AT CSS 03 |
| Mod A00040· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-01-28 | +$19,007 | $25,456,266 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION SA-A00040, INSTALLATION OF ADDITIONAL IRRIGATION REQUIREMENTS |
| Mod A00041· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-02-07 | +$739 | $25,457,005 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION SA-A00041, INCREASED COSTS DUE TO COVID ? SUPPLY ISSUES (WEBER COMPANY… |
| Mod A00042· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-02-07 | +$76,659 | $25,533,664 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION SA-A00042, REVISE SECURITY REQUIREMENTS FOR OWRNC (RFP 010) |
| Mod P00043· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-03-02 | +$317,404 | $25,851,068 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION P00043, UPGRADE ELECTRICAL DISTRIBUTION |
| Mod A00044· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-03-08 | +$13,953 | $25,865,021 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION SA-A00044, INSTALL SIDEWALK AT NEW SALUTING STATUE LOCATION (RFP-13) |
| Mod A00045· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-03-14 | +$4,022 | $25,869,043 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION SA-A00045, REMOVE TREE NEXT TO IRRIGATION MAIN (RFI-085) |
| Mod A00046· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-03-15 | +$7,395 | $25,876,438 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION SA-A00046, ADDITIONAL TESTING REQUIREMENTS (COLUMBARIUM AND BURIAL SEC… |
| Mod A00047· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-03-21 | +$8,928 | $25,885,366 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION SA-A00047, MODIFY FENCING AT SALT STORAGE BIN (RFP-029) |
| Mod A00048· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-03-22 | +$11,871 | $25,897,237 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION SA-A00048, INSTALL SERVICE SEALS IN COMMITTAL SERVICE SHELTER 3 (RFP-0… |
| Mod A00049· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-03-29 | +$5,686 | $25,902,923 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION SA-A00049, MODIFY PUMP HOUSE METAL SIDING (RFI 077) |
| Mod A00050· CHANGE ORDER | 2022-04-21 | +$50,000 | $25,952,923 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION CO-A00050 ABATEMENT OF MOLD ? PUBLIC INFORMATION CENTER BUILDING |
| Mod A00051· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-04-27 | +$0 | $25,952,923 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION AD-A00051, AUTHORIZE MATERIAL OFFSITE STORAGE (PROUT MECHANICAL) |
| Mod A00052· OTHER ADMINISTRATIVE ACTION | 2022-04-29 | +$0 | $25,952,923 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION AD-A00052, WEATHER IMPACT TO SCHEDULE (JANUARY - FEBRUARY 2022) |
| Mod A00053· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-05-02 | +$65,904 | $26,018,827 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION SA-A00053, INSTALL AERATION SYSTEM FOR EXPANSION AREA SOUTH POND (RFP-… |
| Mod A00054· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-05-09 | +$1,064 | $26,019,891 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION SA-A00054, NICHE COVER WASHERS |
| Mod A00055· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-05-11 | +$79,511 | $26,099,402 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION SA-A00055, MODIFY ADMINISTRATION TEMPORARY TRAILER (RFP-022) |
| Mod A00056· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-06-03 | +$48,876 | $26,148,278 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION SA-A00056, REGRADE MAINTENANCE YARD DRAINAGE (RFP-025) |
| Mod A00057· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-06-09 | +$3,628 | $26,151,906 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION SA-A00057, PROVIDE ADDITIONAL CLEANING OF TEMPORARY RESTROOMS FOR MEMO… |
| Mod A00058· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-06-13 | +$168,498 | $26,320,404 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION SA-A00058, INCORPORATE SERVICE SEALS INTO FLAG ASSEMBLY AREA AND COMMI… |
| Mod A00059· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-06-15 | +$62,635 | $26,383,039 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION SA-A00059, UPGRADE GNSS RECEIVER/ROVER UNITS TO TRIMBLE R12 CAPABILITI… |
| Mod A00060· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-06-27 | +$8,572 | $26,391,611 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION SA-A00060, REPAIR COLUMBARIUM STONE (RFP-033) |
| Mod A00061· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-06-30 | +$126,263 | $26,517,874 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION SA-A00061, MODIFY ADMINISTRATION AND MAINTENANCE BUILDING (RFP 031) |
| Mod A00062· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-07-15 | +$17,251 | $26,535,125 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION SA-A00062, REPLACE CATCH BASIN |
| Mod A00063· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-07-22 | +$4,068 | $26,539,193 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION SA-A00063, RELOCATE GAS LINE |
| Mod A00064· DEFINITIZE CHANGE ORDER | 2022-07-26 | +$53,412 | $26,592,605 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION SA-A00064, REMEDIATE AND RECONSTRUCT PUBLIC INFORMATION CENTER (MOLD R… |
| Mod A00065· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-08-02 | +$16,461 | $26,609,066 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION SA-A00065, REGRADE MAIN ENTRANCE MOUNDS |
| Mod A00066· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-08-02 | +$8,716 | $26,617,782 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION SA-A00066, RECONFIGURE TRAFFIC AND WAYFINDING FOR TEMPORARY PIC TRAILE… |
| Mod A00067· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-08-08 | +$42,549 | $26,660,331 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION SA-A00067, REPLACE UNSATISFACTORY SOILS AT FRONT ENTRANCE (SEQUENCE A) |
| Mod A00068· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-08-24 | +$8,077 | $26,668,408 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION SA-A00068, REPLACE ASPHALT WITH CONCRETE AT FUEL TANKS (RFP 034) |
| Mod A00069· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-08-25 | +$12,375 | $26,680,783 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION SA-A00069, INSTALL ADDITIONAL IRRIGATION |
| Mod A00070· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-09-12 | +$8,663 | $26,689,446 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION SA-A00070, RELOCATE POWER AND CONTROLS FOR IRRIGATION WELL 1 |
| Mod A00071· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-10-25 | +$1,720 | $26,691,166 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION SA-A00071, PAINT EXISTING EXTERIOR OF PIC (RFI 151) |
| Mod P00072· CHANGE ORDER | 2022-12-30 | +$600,000 | $27,291,166 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION CHANGE ORDER, P00072, REPAIR STONE VENEER OF PUBLIC INFORMATION CENTER |
| Mod A00073· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2023-01-04 | +$70,366 | $27,361,532 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION SA-A00073, RELOCATE EXISTING IRRIGATION DUE TO NEW CURB INSTALLATION (… |
| Mod A00074· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2023-01-04 | +$19,751 | $27,381,283 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION SA-A00074, INSTALL ADDITIONAL SOD ALONG SECTIONS 14 AND G3 NEW CURBS (… |
| Mod A00075· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2023-01-09 | +$18,781 | $27,400,064 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION SA-A00075, INSTALL CURB AT COLUMBARIUM F (RFI-141) AND CORRECT ACCOUNTI… |
| Mod A00076· CHANGE ORDER | 2023-01-19 | +$10,000 | $27,410,064 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION CO-A00076, CHANGE PROJECT MANAGEMENT SOFTWARE TO KAHUA FROM TRIRIGA |
| Mod A00077· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2023-01-31 | +$38,659 | $27,448,723 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION SA-A00077, INSTALL ADDITIONAL ELECTRICAL IN PIC AND ADMIN SWING SPACE (… |
| Mod A00078· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2023-02-06 | +$6,733 | $27,455,456 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION SA-A00078, REPLACE PIC FIRE ALARM PANEL (VCI094) |
| Mod A00079· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2023-02-10 | +$19,069 | $27,474,525 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION SA-A00079, INSPECT GRANITE NICHE COVERS (VCI097) |
| Mod A00080· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2023-02-21 | +$4,636 | $27,479,161 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION SA-A00080, CONDUCT SURVEY OF EXISTING STORMWATER LINES (VCI098) |
| Mod A00081· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2023-02-24 | +$5,546 | $27,484,707 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION SA-A00081, MISCELLANEOUS ADMIN BUILDING COSTS (VCI099) |
| Mod A00082· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2023-03-06 | +$7,279 | $27,491,986 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION SA-A00082, RELOCATE FLORAL DISPOSAL AREA CHAIN LINK FENCING (VCI100) |
| Mod A00083· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2023-03-14 | +$11,999 | $27,503,985 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION SA-A00083, REPLACE MECHANICAL ROOM LIGHT FIXTURES (VCI101R1) |
| Mod A00084· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2023-03-15 | +$4,235 | $27,508,220 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION SA-A00084, MODIFY FLOORING IN ADMIN/MAINTENANCE BUILDING |
| Mod A00085· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2023-03-23 | +$55,551 | $27,563,771 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION SA-A00085, EXTEND TEMPORARY RESTROOM AND RECEPTION TRAILERS |
| Mod P00086· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2023-04-03 | +$237,057 | $27,800,828 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION EQUITABLE ADJUSTMENT FOR GIS AND FOR TESTING REA VCI-063R AND VCI-105… |
| Mod A00087· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2023-04-05 | +$25,761 | $27,826,589 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION SA-A00087, REPAIR CSS#3 CONCRETE (RFP-039) |
| Mod A00088· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2023-05-09 | +$10,809 | $27,837,398 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION SA-A00088 (RFI 129) ADDITIONAL TILE WORK AT PIC |
| Mod A00089· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2023-05-09 | +$2,956 | $27,840,354 | OHIO WESTERN RESERVE PH 3 CONSTRUCTION SA-A00089, REPAIR LANDSCAPE AND ELECTRIC AT WELL #2 DRAIN LINE |
| Mod P00090· OTHER ADMINISTRATIVE ACTION | 2023-06-09 | +$0 | $27,840,354 | VA TRANSITION TO A NEW FINANCIAL AND ACQUISITION MANAGEMENT SYSTEM, IFAMS |
| Mod P00093· CHANGE ORDER | 2023-07-20 | +$150,000 | $27,990,354 | UNILATERAL CHANGE ORDER TO DIRECTOR CONTRACTOR TO PROCEED WITH TEMPORARY COMMITTAL SHELTER |
| Mod A00091· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2023-07-27 | +$66,097 | $28,056,451 | REGRADE MEMORIAL WALKWAY |
| Mod A00092· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2023-07-27 | +$6,761 | $28,063,212 | FURNISH ADDITIONAL COMMITTAL SHELTER BENCHES FOR CSS#1 & #2 |
| Mod A00094· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2023-08-01 | +$55,167 | $28,118,379 | OHIO WESTERN RESERVE PHASE III CONSTRUCTION SA-A00094, REMOVE AND REPLACE GUARDRAIL ALONG LIBERTY ROAD |
| Mod A00095· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2023-08-15 | +$76,824 | $28,195,203 | OHIO WESTERN RESERVE PHASE III CONSTRUCTION SA-A00095, INSTALL UPDATED DIRECTORIES AND CEMETERY POLICY SIGNAGE |
| Mod A00096· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2023-09-22 | +$54,540 | $28,249,743 | OHIO WESTERN RESERVE PHASE III CONSTRUCTION SA-A00096 (RFP-042, ASSESS PUMP INTAKE SEDIMENT AND DREDGE POND) |
| Mod A00097· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2023-09-29 | +$19,937 | $28,269,680 | OHIO WESTERN RESERVE PHASE III CONSTRUCTION SA-A00097 (PROVIDE ADDITIONAL ADMIN TRAILER SPACE RENTAL) |
| Mod A00098· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2023-11-03 | +$49,769 | $28,319,449 | OHIO WESTERN RESERVE PHASE III CONSTRUCTION SA-A00098 (MODIFY GRADES AND ADJUST IRRIGATION AT CARILLON TOWER) |
| Mod A00099· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2023-12-13 | +$33,868 | $28,353,317 | OHIO WESTERN RESERVE PHASE III CONSTRUCTION SA-A00099 (RE-BASELINE SCHEDULE, RE-ALIGN CSS#3 SPEAKERS, REMOVE A… |
| Mod A00101· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2024-01-24 | +$196,556 | $28,549,873 | OHIO WESTERN RESERVE PHASE III CONSTRUCTION SA-A00101 (REPAIRS AND EXTENSIONS OF IRRIGATION SYSTEM) |
| Mod A00102· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2024-02-12 | +$187,497 | $28,737,370 | OHIO WESTERN RESERVE PHASE III CONSTRUCTION A00102 (FINALIZED TEMPORARY COMMITTAL SHELTER AND PIC RECONSTRUCTI… |
| Mod A00103· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2024-02-14 | +$95,546 | $28,832,916 | INSTALL MW WAYFINDING AND NEW SINGLE MODE FIBER OPTIC CABLE |
| Mod A00104· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2024-05-07 | +$244,271 | $29,077,187 | ADDITIONAL NORTH COLUMBARIA AND ADMINISTRATIVE REPAIRS |
| Mod A00105· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2024-05-07 | +$185,785 | $29,262,972 | ADDITIONAL SOUTH COLUMBARIA AND ADMINISTRATIVE REPAIRS |
| Mod A00107· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2024-11-13 | +$120,114 | $29,383,086 | SA-A00107 ADDITIONAL SECURITY, FIRE PROTECTION, AND HVAC ENHANCEMENTS |
| Mod A00108· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2024-12-17 | +$43,502 | $29,426,588 | SA-A00108 IRRIGATION SYSTEM REPAIRS AND FINAL LOOP TUNING |
| Mod A00100· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2024-12-23 | +$0 | $29,426,588 | OHIO WESTERN RESERVE PHASE III CONSTRUCTION A00100 (NO COST MOD FOR STORMWATER AND SITE WORK, RFIS 136 AND 137… |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI JEJJZPGM2CJ7)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| 36C25026C0134 | 250-NETWORK CONTRACT OFFICE 10 (36C250) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $9,039,000 | FY2026 |
| 36C25026C0113 | 250-NETWORK CONTRACT OFFICE 10 (36C250) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $3,698,950 | FY2026 |
| 36C25026P0382 | 250-NETWORK CONTRACT OFFICE 10 (36C250) · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES | $211,754 | FY2026 |
| 36C25025C0151 | 250-NETWORK CONTRACT OFFICE 10 (36C250) · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES | $10,699,000 | FY2025 |
| 36C25025P1219 | 250-NETWORK CONTRACT OFFICE 10 (36C250) · J045 · MAINT/REPAIR/REBUILD OF EQUIPMENT- PLUMBING, HEATING, AND WASTE DISPOSAL EQUIPMENT | $39,750 | FY2025 |
| 36C25025C0075 | 250-NETWORK CONTRACT OFFICE 10 (36C250) · Z2NB · REPAIR OR ALTERATION OF HEATING AND COOLING PLANTS | $12,467,574 | FY2025 |
Other recipients under Y1PC from OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| 36C10F26C0005 | GC & V CONSTRUCTION LLC | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $59,890,000 | FY2026 |
| 36C10F25C0007 | HAMILTON PACIFIC CHAMBERLAIN LLC | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $637,437 | FY2025 |
| 36C10F24C0007 | SEABEE CONSTRUCTION, INC. | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $79,106,191 | FY2024 |
| 36C10F24C0001 | RBVETCO, LLC | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $38,940,668 | FY2024 |
| 36C10F23C0008 | SGC SERVICES 2, LLC | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $42,010,850 | FY2023 |