Award recordCONTRACT

GLOBAL URBAN ENTERPRISES, L.L.C.

PIID 36C10F19C0015· VA Staff Offices· OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F)· Y1PC · CONSTRUCTION OF UNIMPROVED REAL PROPERTY (LAND)· FY2019· $24,336,157 net obligations· UEI XTXHYTLBGTK8· NY

Description

A00026.SA 20 FINAL BOND PREMIUM ADJUSTMENT

Base award description: CONSTRUCTION OF WESTERN NEW YORK NATIONAL CEMETERY, PEMBROKE, NEW YORK

First action · last action
2019-08-16 · 2024-05-16
Transactions
25
First transaction's obligation
$23,337,281
Base + all options value (sum of deltas)
$47,571,938
Extent competed
FULL AND OPEN COMPETITION AFTER EXCLUSION OF SOURCES
Other than full & open authority
—
Set-aside
SERVICE DISABLED VETERAN OWNED SMALL BUSINESS SET-ASIDE
Offers received
2
SDVOSB flag on record
Yes (self-representation)
NAICS
237990 · OTHER HEAVY AND CIVIL ENGINEERING CONSTRUCTION

Modification chain · 25 transactions

Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.

$24,336,157$0Base award · 2019-08-16 · this action $23,337,281 · running total $23,337,281Modification A00001 · 2020-04-13 · this action $3,500 · running total $23,340,781Modification A00002 · 2020-04-13 · this action $37,000 · running total $23,377,781Modification A00003 · 2020-04-13 · this action $61,000 · running total $23,438,781Modification A00005 · 2020-04-13 · this action $209,000 · running total $23,647,781Modification A00004 · 2022-03-15 · this action $17,000 · running total $23,664,781Modification A00007 · 2022-03-15 · this action $56,730 · running total $23,721,511Modification A00009 · 2022-03-15 · this action $82,000 · running total $23,803,511Modification A00010 · 2022-03-15 · this action $79,861 · running total $23,883,372Modification A00011 · 2022-03-15 · this action $27,572 · running total $23,910,944Modification A00012 · 2022-03-15 · this action $7,001 · running total $23,917,945Modification A00013 · 2022-03-15 · this action $36,377 · running total $23,954,322Modification A00014 · 2022-03-15 · this action $49,026 · running total $24,003,348Modification A00015 · 2022-03-15 · this action $18,018 · running total $24,021,366Modification A00016 · 2022-03-15 · this action -$216,052 · running total $23,805,314Modification A00006 · 2023-05-30 · this action $73,671 · running total $23,878,985Modification A00008 · 2023-05-30 · this action $37,968 · running total $23,916,953Modification A00020 · 2023-05-30 · this action $33,321 · running total $23,950,274Modification A00021 · 2023-05-30 · this action $33,864 · running total $23,984,138Modification A00022 · 2023-05-30 · this action $45,426 · running total $24,029,564Modification A00024 · 2023-05-30 · this action $59,122 · running total $24,088,686Modification A00025 · 2023-05-30 · this action $200,000 · running total $24,288,686Modification P00005 · 2023-06-09 · this action $0 · running total $24,288,686Modification A00017 · 2023-09-27 · this action $37,581 · running total $24,326,267Modification A00026 · 2024-05-16 · this action $9,890 · running total $24,336,157
  • Base2019-08-16+$23,337,281= $23,337,281
  • Mod A000012020-04-13+$3,500= $23,340,781
  • Mod A000022020-04-13+$37,000= $23,377,781
  • Mod A000032020-04-13+$61,000= $23,438,781
  • Mod A000052020-04-13+$209,000= $23,647,781
  • Mod A000042022-03-15+$17,000= $23,664,781
  • Mod A000072022-03-15+$56,730= $23,721,511
  • Mod A000092022-03-15+$82,000= $23,803,511
  • Mod A000102022-03-15+$79,861= $23,883,372
  • Mod A000112022-03-15+$27,572= $23,910,944
  • Mod A000122022-03-15+$7,001= $23,917,945
  • Mod A000132022-03-15+$36,377= $23,954,322
  • Mod A000142022-03-15+$49,026= $24,003,348
  • Mod A000152022-03-15+$18,018= $24,021,366
  • Mod A000162022-03-15-$216,052= $23,805,314
  • Mod A000062023-05-30+$73,671= $23,878,985
  • Mod A000082023-05-30+$37,968= $23,916,953
  • Mod A000202023-05-30+$33,321= $23,950,274
  • Mod A000212023-05-30+$33,864= $23,984,138
  • Mod A000222023-05-30+$45,426= $24,029,564
  • Mod A000242023-05-30+$59,122= $24,088,686
  • Mod A000252023-05-30+$200,000= $24,288,686
  • Mod P000052023-06-09+$0= $24,288,686
  • Mod A000172023-09-27+$37,581= $24,326,267
  • Mod A000262024-05-16+$9,890= $24,336,157
TransactionAction dateThis action (delta)Running totalDescription on this transaction
Base2019-08-16+$23,337,281$23,337,281CONSTRUCTION OF WESTERN NEW YORK NATIONAL CEMETERY, PEMBROKE, NEW YORK
Mod A00001· CHANGE ORDER2020-04-13+$3,500$23,340,781A00001.CO-01A SURVEY EXISTING HOUSE ON THE PROPERTY FOR ASBESTOS AND LEAD.
Mod A00002· CHANGE ORDER2020-04-13+$37,000$23,377,781A00002.CO-01B - REMOVE ASBESTOS FROM THE EXISTING HOUSE AND DEMO THE HOUSE.
Mod A00003· CHANGE ORDER2020-04-13+$61,000$23,438,781A00003.CO-01C - USE UNSUITABLE NONSTRUCTURAL FILL AT LOW SPOT EAST OF MAIN ENTRY
Mod A00005· CHANGE ORDER2020-04-13+$209,000$23,647,781CONSTRUCTION OF WESTERN NEW YORK NATIONAL CEMETERY, PEMBROKE, NEW YORK
Mod A00004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2022-03-15+$17,000$23,664,781A00004.SA#01 - STONE BACKFILL OF STORM PIPE DURING WINTER MONTHS WHEN SOIL TOO WET
Mod A00007· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2022-03-15+$56,730$23,721,511A00007.CO-01G IRRIGATION PUMP ELECTRIC FEEDER SIZE INCREASE
Mod A00009· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2022-03-15+$82,000$23,803,511A00009.CO-01H - GARAGE ELECTRIC SVC
Mod A00010· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2022-03-15+$79,861$23,883,372A00010.SA-04 - UNDERCUT 1'-0" WET SOIL BELOW PPC FIELDS
Mod A00011· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2022-03-15+$27,572$23,910,944A00011.SA-05 TERRAZZO AT TOILET ROOMS
Mod A00012· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2022-03-15+$7,001$23,917,945A00012.SA-06 GARAGE ELEC SVC (A00009.CO-01H)
Mod A00013· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2022-03-15+$36,377$23,954,322A00013.SA-07 GARAGE SOG
Mod A00014· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2022-03-15+$49,026$24,003,348A00014.SA-08 CHANGE FROM ALVERSON STONE TO INDIAN FIELDS STONE
Mod A00015· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2022-03-15+$18,018$24,021,366A00015.SA-09 IRRIGATION PUMP FEEDER (A00007.CO-01G)
Mod A00016· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2022-03-15−$216,052$23,805,314A00004.SA#01 - STONE BACKFILL OF STORM PIPE DURING WINTER MONTHS WHEN SOIL TOO WET
Mod A00006· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2023-05-30+$73,671$23,878,985A00006.SA-02
Mod A00008· DEFINITIZE CHANGE ORDER2023-05-30+$37,968$23,916,953A00008.SA-03 - DEF A00003.CO-01C
Mod A00020· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2023-05-30+$33,321$23,950,274A00020.SA-14 ADDITIONAL ELECTRICAL WORK
Mod A00021· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2023-05-30+$33,864$23,984,138A00021.SA -15 IRRIGATION CHANGES
Mod A00022· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2023-05-30+$45,426$24,029,564A00022.SA-16 MISC ADMIN BLDG CHANGES
Mod A00024· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2023-05-30+$59,122$24,088,686A00024.SA -18 NO PAINTING IN SPECIFICATIONS
Mod A00025· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2023-05-30+$200,000$24,288,686A00025.SA -19 STONE CHANGE ALVERSON TO INDIAN FIELDS
Mod P00005· OTHER ADMINISTRATIVE ACTION2023-06-09+$0$24,288,686A00025.SA -19 STONE CHANGE ALVERSON TO INDIAN FIELDS
Mod A00017· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2023-09-27+$37,581$24,326,267A00017.SA -11 FIBER TO MAINTENANCE TRAILER, UTILITIES AND PLAQUES DEF A00001.CO-01C AND A00002.CO-01B
Mod A00026· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2024-05-16+$9,890$24,336,157A00026.SA 20 FINAL BOND PREMIUM ADJUSTMENT

Related awards · 11

Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.

Other VA awards to the same recipient (UEI XTXHYTLBGTK8)

AwardOffice · PSC / listingNet obligationsFY
36C78625C0038NATIONAL CEMETERY ADMIN (36C786) · Y1JZ · CONSTRUCTION OF MISCELLANEOUS BUILDINGS$2,423,357FY2025
36C78625C50100NATIONAL CEMETERY ADMIN (36C786) · Y1AZ · CONSTRUCTION OF OTHER ADMINISTRATIVE FACILITIES AND SERVICE BUILDINGS$2,546FY2025
36C10F23C0010OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) · Y1EB · CONSTRUCTION OF MAINTENANCE BUILDINGS$24,717,925FY2023
36C24223C0157242-NETWORK CONTRACT OFFICE 02 (36C242) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES$74,500FY2023
36C24823D0029248-NETWORK CONTRACT OFFICE 8 (36C248) · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES$0FY2023
36C10F23C0001OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) · Y1LB · CONSTRUCTION OF HIGHWAYS, ROADS, STREETS, BRIDGES, AND RAILWAYS$425,589FY2023

Other recipients under Y1PC from OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) (most recent first)

AwardRecipientOfficeNet obligationsFY
36C10F26C0005GC & V CONSTRUCTION LLCOFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F)$59,890,000FY2026
36C10F25C0007HAMILTON PACIFIC CHAMBERLAIN LLCOFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F)$637,437FY2025
36C10F24C0007SEABEE CONSTRUCTION, INC.OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F)$79,106,191FY2024
36C10F24C0001RBVETCO, LLCOFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F)$38,940,668FY2024
36C10F23C0008SGC SERVICES 2, LLCOFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F)$42,010,850FY2023