Award recordCONTRACT

C & C CONTRACTORS LLC

PIID 36C10F19C0013· VA Staff Offices· OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F)· Y1KZ · CONSTRUCTION OF OTHER CONSERVATION AND DEVELOPMENT FACILITIES· FY2019· $40,389,916 net obligations· UEI Z6ZVR3MXC9L4· AL

Description

P00021 - BOND PREMIUM ADJUSTMENT, MISC. CHANGES

Base award description: EXPAND ABRAHAM LINCOLN NATIONAL CEMETERY TO PROVIDE APPROXIMATELY 10 MORE YEARS OF INTERMENT CAPACITY.

First action · last action
2019-09-30 · 2025-03-10
Transactions
23
First transaction's obligation
$34,261,000
Base + all options value (sum of deltas)
$40,389,916
Extent competed
FULL AND OPEN COMPETITION AFTER EXCLUSION OF SOURCES
Other than full & open authority
—
Set-aside
SMALL BUSINESS SET ASIDE - TOTAL
Offers received
4
SDVOSB flag on record
Yes (self-representation)
NAICS
237990 · OTHER HEAVY AND CIVIL ENGINEERING CONSTRUCTION

Modification chain · 23 transactions

Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.

$40,389,916$0Base award · 2019-09-30 · this action $34,261,000 · running total $34,261,000Modification P00001 · 2021-04-13 · this action -$60,098 · running total $34,200,903Modification P00002 · 2021-07-30 · this action $84,490 · running total $34,285,393Modification P00003 · 2021-10-21 · this action $334,737 · running total $34,620,129Modification A00004 · 2021-12-07 · this action $96,225 · running total $34,716,354Modification P00005 · 2021-12-08 · this action $201,220 · running total $34,917,574Modification P00006 · 2021-12-08 · this action $172,077 · running total $35,089,651Modification A00002 · 2021-12-13 · this action $0 · running total $35,089,651Modification P00007 · 2022-01-03 · this action $634,000 · running total $35,723,651Modification A00008 · 2022-06-17 · this action $15,847 · running total $35,739,498Modification P00009 · 2022-07-07 · this action $125,000 · running total $35,864,498Modification P00010 · 2022-07-26 · this action $296,094 · running total $36,160,592Modification P00011 · 2022-08-03 · this action $183,142 · running total $36,343,734Modification P00012 · 2022-08-04 · this action $368,692 · running total $36,712,426Modification P00013 · 2022-08-17 · this action $188,439 · running total $36,900,865Modification P00018 · 2023-08-18 · this action $1,570,030 · running total $38,470,895Modification P00017 · 2023-09-14 · this action $264,724 · running total $38,735,619Modification A00014 · 2024-01-17 · this action $90,414 · running total $38,826,033Modification A00015 · 2024-01-17 · this action $14,320 · running total $38,840,353Modification A00016 · 2024-01-17 · this action $68,345 · running total $38,908,698Modification P00019 · 2024-09-13 · this action $1,388,583 · running total $40,297,281Modification P00020 · 2024-09-26 · this action $23,353 · running total $40,320,633Modification P00021 · 2025-03-10 · this action $69,283 · running total $40,389,916
  • Base2019-09-30+$34,261,000= $34,261,000
  • Mod P000012021-04-13-$60,098= $34,200,903
  • Mod P000022021-07-30+$84,490= $34,285,393
  • Mod P000032021-10-21+$334,737= $34,620,129
  • Mod A000042021-12-07+$96,225= $34,716,354
  • Mod P000052021-12-08+$201,220= $34,917,574
  • Mod P000062021-12-08+$172,077= $35,089,651
  • Mod A000022021-12-13+$0= $35,089,651
  • Mod P000072022-01-03+$634,000= $35,723,651
  • Mod A000082022-06-17+$15,847= $35,739,498
  • Mod P000092022-07-07+$125,000= $35,864,498
  • Mod P000102022-07-26+$296,094= $36,160,592
  • Mod P000112022-08-03+$183,142= $36,343,734
  • Mod P000122022-08-04+$368,692= $36,712,426
  • Mod P000132022-08-17+$188,439= $36,900,865
  • Mod P000182023-08-18+$1,570,030= $38,470,895
  • Mod P000172023-09-14+$264,724= $38,735,619
  • Mod A000142024-01-17+$90,414= $38,826,033
  • Mod A000152024-01-17+$14,320= $38,840,353
  • Mod A000162024-01-17+$68,345= $38,908,698
  • Mod P000192024-09-13+$1,388,583= $40,297,281
  • Mod P000202024-09-26+$23,353= $40,320,633
  • Mod P000212025-03-10+$69,283= $40,389,916
TransactionAction dateThis action (delta)Running totalDescription on this transaction
Base2019-09-30+$34,261,000$34,261,000EXPAND ABRAHAM LINCOLN NATIONAL CEMETERY TO PROVIDE APPROXIMATELY 10 MORE YEARS OF INTERMENT CAPACITY.
Mod P00001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2021-04-13−$60,098$34,200,903SA P00001 - INCLUDES PCO 00001: MISC DESIGN DHANGES (DESIGN BUILD) AND PCO 00003: PARALLEL PARKING AT COLUMBAR…
Mod P00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2021-07-30+$84,490$34,285,393SA P00002, INCLUDES PCO 00017 TRAFFIC AND NOISE IMPACT MITIGATION DESIGN
Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2021-10-21+$334,737$34,620,129SA P00003, MOVE OS VAULT FIELD AND TRADITIONAL FIELD FROM NORTH OF PROPERTY TO SOUTHEAST CORNER OF PROPERTY AN…
Mod A00004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2021-12-07+$96,225$34,716,354SA A00004, REMOVAL OF EXCESS UNSUITABLE SOILS NOT IDENTIFIED IN THE ORIGINAL SCOPE.
Mod P00005· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2021-12-08+$201,220$34,917,574P00005 - CONNECTOR ROAD-PARKING LOT SUBGRADE STABILIZATION (THIS IS THE EXTENSION OF WASHINGTON TO THE NEW RR…
Mod P00006· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2021-12-08+$172,077$35,089,651P00006 ROAD BED LIME STABILIZATION
Mod A00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2021-12-13+$0$35,089,651SA A00002: THIS MODIFICATION IS ISSUED TO PROVIDE UPDATED SPECIFICATIONS FOR SECTIONS: 01 45 00 QUALITY CONTRO…
Mod P00007· CHANGE ORDER2022-01-03+$634,000$35,723,651P00007 WELL ISSUES AND VOID COUNTERMEASURES, UNFORESEEN CONDITION TY 2
Mod A00008· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2022-06-17+$15,847$35,739,498A00008 WASHINGTON RD LIME STABILIZATION
Mod P00009· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2022-07-07+$125,000$35,864,498P00007 WELL ISSUES AND VOID COUNTERMEASURES, UNFORESEEN CONDITION TY 2
Mod P00010· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2022-07-26+$296,094$36,160,592P00010: PHYSICAL SECURITY UPDATES
Mod P00011· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2022-08-03+$183,142$36,343,734P00011: DELETE SEPTIC TANK AND FORCE MAIN
Mod P00012· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2022-08-04+$368,692$36,712,426P00012: DUCT BANK CHANGES
Mod P00013· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2022-08-17+$188,439$36,900,865P00013: ADMIN BLDG SWING SPACE
Mod P00018· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2023-08-18+$1,570,030$38,470,895P00018: TRUCK TURN AROUND
Mod P00017· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2023-09-14+$264,724$38,735,619P00017: WALTER STRAWN ENTRANCE AND MISC.
Mod A00014· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2024-01-17+$90,414$38,826,033A00014 UNSUITABLE SOILS AT SHOULDER LOOP
Mod A00015· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2024-01-17+$14,320$38,840,353A00015:CHANGE GNSS DATA COLLECTION ROVERS
Mod A00016· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2024-01-17+$68,345$38,908,698A00016:CORRECT UNSUITABLE SOILS AT JEFFERSON ROAD AND CORTEGE LANE
Mod P00019· DEFINITIZE CHANGE ORDER2024-09-13+$1,388,583$40,297,281P00019 - DEFINITIZE CHANGE ORDER P00007 FOR WELL DIFFERING SITE CONDITIONS
Mod P00020· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2024-09-26+$23,353$40,320,633P00020 - COMED UTILITY FEE
Mod P00021· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2025-03-10+$69,283$40,389,916P00021 - BOND PREMIUM ADJUSTMENT, MISC. CHANGES

Related awards · 6

Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.

Other VA awards to the same recipient (UEI Z6ZVR3MXC9L4)

AwardOffice · PSC / listingNet obligationsFY
36C78626C0020NATIONAL CEMETERY ADMIN (36C786) · Y1AZ · CONSTRUCTION OF OTHER ADMINISTRATIVE FACILITIES AND SERVICE BUILDINGS$31,145,450FY2026
36C24726C0055247-NETWORK CONTRACT OFFICE 7 (36C247) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES$9,079,864FY2026
36C78626N0338NATIONAL CEMETERY ADMIN (36C786) · Y1AZ · CONSTRUCTION OF OTHER ADMINISTRATIVE FACILITIES AND SERVICE BUILDINGS$122,570FY2026
36C78626N0342NATIONAL CEMETERY ADMIN (36C786) · Z2JZ · REPAIR OR ALTERATION OF MISCELLANEOUS BUILDINGS$361,151FY2026
36C78625C0042NATIONAL CEMETERY ADMIN (36C786) · Y1JZ · CONSTRUCTION OF MISCELLANEOUS BUILDINGS$24,203,981FY2025
36C78625N0565NATIONAL CEMETERY ADMIN (36C786) · Y1AZ · CONSTRUCTION OF OTHER ADMINISTRATIVE FACILITIES AND SERVICE BUILDINGS$281,750FY2025

Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_36C10F19C0013_3600_-NONE-_-NONE- · retrieved 2026-09-26.